Full-line testing on the East Extension is under way, seven years after the contract was signed. Here’s what Line 1 riders will notice, and why Orléans is still waiting
If you rode the O-Train this week and did a double take at the destination sign, no, you’re not dreaming. Since Sunday, November 22, eastbound trains have been showing Trim Station as the last stop.
The catch: you still can’t go there. Everyone off at Blair, same as always. The train then carries on east without you, a big empty tease rolling off toward Orléans.
Don’t despair, it’s all part of OC Transpo’s “full-line testing” for the O-Train East Extension. Trains are now running the whole length of Line 1, from Tunney’s Pasture to Trim, so the city can stress-test the vehicles, the schedules and the staffing before anyone is actually allowed to ride past Blair.
What you’ll notice on Line 1
- Signs that say Trim. Destination signs and next-departure screens list Trim as the final eastbound stop. Ignore them for now and get off at Blair.
- More trains, sometimes. Service may run more often at certain times while testing is on.
- Double-car trains on some weekends. Enjoy the elbow room.
- New signage. Stations are getting updated wayfinding that shows Trim as the new eastern end of the line.
- Friendly faces at Blair. OC Transpo staff will be on the platform to point confused riders in the right direction.
One more thing to know: trains won’t run on the East Extension at all during the week of November 29. East-West Connectors, the builder, asked for the pause so it can upgrade the track, which should help reliability. Testing picks up again once that work is done. Regular Line 1 service between Tunney’s Pasture and Blair isn’t affected.
So… how long has the O-Train East Extension taken?
Grab a coffee. The East Extension adds 12.5 km of track and five new stations past Blair: Montréal, Jeanne d’Arc, Convent Glen, Place d’Orléans and Trim. The city hired East-West Connectors, a Kiewit-Vinci joint venture, to build it back in spring 2019. At the time, the plan was to open it in 2024.
Here’s how that went:
- 2019: Contract signed, crews mobilize. Opening target: 2024.
- October 2022: Crews connect the Line 1 rails to the new extension near Blair.
- February 2024: An O-Train rolls east of Blair for the first time, slowly.
- 2024 to 2025: The opening date slides to spring 2025, then summer 2025, then the end of 2025, then “early 2026.”
- March 4, 2026: The builder reaches substantial completion. In other words, the line is built.
- Spring and summer 2026: Trial running stalls. A bearing problem known as spalling sidelines much of the Line 1 fleet, leaving too few trains for regular service, let alone testing a new line.
- November 22, 2026: Full-line testing to Trim begins.
That’s about seven and a half years since the contract was signed, and roughly three years past the original opening target. There’s still no official opening date. City leaders have said, more than once, that after the Stage 1 saga and the public inquiry that followed, they’d rather open it late than open it broken. Orléans commuters have heard “soon” before, but this time the trains really are running to Trim! They just aren’t stopping for you yet.
What happens next
Full-line testing should last a few weeks. During that time OC Transpo runs the trains, timetables and staff across the whole line to shake out problems before moving to the next phase. It’s the same step-by-step approach the city used before opening Lines 2 and 4.
Expect a few hiccups. If testing turns up an issue that Rideau Transit Maintenance or East-West Connectors needs to fix, trains between Blair and Trim may stop running for a bit. OC Transpo says that’s normal, and that keeping regular Line 1 service running comes first.
So, Orléans: the train is finally going your way. It just isn’t picking you up yet. Keep that Trim Station Park and Ride spot in mind. It’s getting closer.